1 00:00:16,099 --> 00:00:13,730 Saturn five quarterly film reports 2 00:00:19,450 --> 00:00:16,109 number six covers progress during the 3 00:00:21,980 --> 00:00:19,460 period March April and May 1964 4 00:00:27,769 --> 00:00:21,990 highlighting Saturn ground test stage 5 00:00:30,290 --> 00:00:27,779 construction prime contractor for the 6 00:00:32,659 --> 00:00:30,300 s1c is Boeing aircraft company 7 00:00:36,709 --> 00:00:32,669 responsible for fabrication and assembly 8 00:00:41,150 --> 00:00:36,719 of ten of the 14 presently scheduled s1c 9 00:00:43,610 --> 00:00:41,160 stages the remaining stages are being or 10 00:00:46,790 --> 00:00:43,620 will be assembled by Marshall using 11 00:00:48,979 --> 00:00:46,800 Boeing supplied components s1c efforts 12 00:00:51,380 --> 00:00:48,989 at Marshall this quarter were primarily 13 00:00:54,860 --> 00:00:51,390 in support of the test fuel tank and the 14 00:00:56,900 --> 00:00:54,870 static test stage on March 6th the test 15 00:00:58,880 --> 00:00:56,910 fuel tank was removed from the vertical 16 00:01:01,670 --> 00:00:58,890 Assembly Building where the forward and 17 00:01:03,830 --> 00:01:01,680 aft adaptors had been attached that was 18 00:01:06,350 --> 00:01:03,840 moved to the center's structural test 19 00:01:08,990 --> 00:01:06,360 area here the tank was placed in the 20 00:01:10,490 --> 00:01:09,000 test stand and preparations began for 21 00:01:13,160 --> 00:01:10,500 the structural testing which is 22 00:01:15,170 --> 00:01:13,170 scheduled in June the first phase of the 23 00:01:18,830 --> 00:01:15,180 test program will be a full pressure 24 00:01:22,789 --> 00:01:18,840 hydrostatic test / vibration and burst 25 00:01:26,749 --> 00:01:22,799 tests will be conducted later Assembly 26 00:01:29,420 --> 00:01:26,759 of the s1 CT static test stage continued 27 00:01:31,399 --> 00:01:29,430 to progress during the report period the 28 00:01:33,289 --> 00:01:31,409 upper half of the fuel tank was moved 29 00:01:36,350 --> 00:01:33,299 into the vertical Assembly Building in 30 00:01:41,179 --> 00:01:36,360 early March and hoisted temporarily into 31 00:01:43,340 --> 00:01:41,189 the hydrostatic tower a week later the 32 00:01:45,980 --> 00:01:43,350 lower half of the fuel tank was moved 33 00:01:52,399 --> 00:01:45,990 into the VAB and positioned on the 34 00:01:55,429 --> 00:01:52,409 rotary turntable in mid-april the upper 35 00:01:59,929 --> 00:01:55,439 and lower halves of the s1 CT fuel tank 36 00:02:02,990 --> 00:01:59,939 were welded together the first of five 37 00:02:06,230 --> 00:02:03,000 locks tunnels for the s1 CT fuel tank 38 00:02:08,180 --> 00:02:06,240 was installed in mid-may the fuel tank 39 00:02:10,430 --> 00:02:08,190 had been moved to the hydrostatic tower 40 00:02:12,559 --> 00:02:10,440 for this operation so that the vertical 41 00:02:13,820 --> 00:02:12,569 assembly buildings rotary turntable 42 00:02:18,560 --> 00:02:13,830 would be available for 43 00:02:20,750 --> 00:02:18,570 on the s-1 Satie lot tank completion of 44 00:02:25,700 --> 00:02:20,760 locks tunnel installation is expected 45 00:02:28,370 --> 00:02:25,710 early next quarter the lower bulkhead 46 00:02:30,980 --> 00:02:28,380 assembly of the s-1 SAT locks tank was 47 00:02:34,340 --> 00:02:30,990 completed in late May and moved under 48 00:02:36,110 --> 00:02:34,350 the rotary turntable where the lower 49 00:02:40,340 --> 00:02:36,120 intermediate skinned section will be 50 00:02:42,290 --> 00:02:40,350 welded to it next quarter the LOX tank 51 00:02:44,300 --> 00:02:42,300 differs from the fuel tank in the 52 00:02:49,880 --> 00:02:44,310 addition of two intermediate skin 53 00:02:52,160 --> 00:02:49,890 sections welding on the upper bulkhead 54 00:02:56,360 --> 00:02:52,170 assembly was completed near the end of 55 00:02:58,400 --> 00:02:56,370 this report period following welding of 56 00:03:00,740 --> 00:02:58,410 the upper intermediate skin section to 57 00:03:02,900 --> 00:03:00,750 this assembly the upper and lower halves 58 00:03:05,180 --> 00:03:02,910 will be mated in the vertical Assembly 59 00:03:09,820 --> 00:03:05,190 Building next quarter to complete the 60 00:03:16,070 --> 00:03:12,740 installation of the 16 skin panels on 61 00:03:18,259 --> 00:03:16,080 the s-1 CT thrust structure has now been 62 00:03:22,750 --> 00:03:18,269 completed installation of the heat 63 00:03:27,890 --> 00:03:25,250 component hardware for the s-1 C 64 00:03:30,470 --> 00:03:27,900 structural test stage is being received 65 00:03:34,180 --> 00:03:30,480 at Marshall from Boeing and fuel tank 66 00:03:37,190 --> 00:03:34,190 bulkhead fabrication is underway 67 00:03:39,670 --> 00:03:37,200 construction of Marshalls s1c static 68 00:03:41,990 --> 00:03:39,680 test stand continued during the quarter 69 00:03:45,009 --> 00:03:42,000 completion of initial construction is 70 00:03:48,430 --> 00:03:45,019 expected by the end of this year a 71 00:03:51,530 --> 00:03:48,440 full-size mock-up of the s-1 sea stage 72 00:03:55,759 --> 00:03:51,540 139 feet long and 33 feet in diameter 73 00:03:58,070 --> 00:03:55,769 has been built by Boeing at Michou the 74 00:04:00,320 --> 00:03:58,080 size angle and other measurements of 75 00:04:02,870 --> 00:04:00,330 tubes and wires will be determined from 76 00:04:07,130 --> 00:04:02,880 the mock-up and the information used in 77 00:04:10,400 --> 00:04:07,140 production of flight stages bulkhead 78 00:04:13,340 --> 00:04:10,410 fabrication work for the s1 CD dynamic 79 00:04:18,199 --> 00:04:13,350 test stage is underway by bowing at the 80 00:04:20,150 --> 00:04:18,209 Misha plant fabrication of other s1 C 81 00:04:23,230 --> 00:04:20,160 components continued during the report 82 00:04:25,700 --> 00:04:23,240 period at Boeing Michou and Wichita this 83 00:04:27,530 --> 00:04:25,710 cruciform baffle for example was 84 00:04:31,610 --> 00:04:27,540 manufactured for installation 85 00:04:33,770 --> 00:04:31,620 in the lore of UO bulkhead these 86 00:04:36,200 --> 00:04:33,780 propellant line support structures are 87 00:04:40,070 --> 00:04:36,210 used to support the LOX tunnels in the 88 00:04:42,380 --> 00:04:40,080 thrust structure this adapter fitting 89 00:04:44,570 --> 00:04:42,390 will serve as a terminal fitting for one 90 00:04:47,390 --> 00:04:44,580 arm of the engine actuator support 91 00:04:55,760 --> 00:04:47,400 assembly and as the attach point for the 92 00:04:57,470 --> 00:04:55,770 solid propellant retrorocket at the co 93 00:04:59,780 --> 00:04:57,480 beach facility of north american 94 00:05:02,930 --> 00:04:59,790 aviation space and information systems 95 00:05:05,030 --> 00:05:02,940 division as to manufacturing activities 96 00:05:07,370 --> 00:05:05,040 progressed steadily during this report 97 00:05:10,070 --> 00:05:07,380 period the forward liquid hydrogen 98 00:05:12,590 --> 00:05:10,080 bulkhead for the s2s stage was 99 00:05:14,510 --> 00:05:12,600 hydrostatically tested and satisfactory 100 00:05:18,020 --> 00:05:14,520 helium leak detection tests were 101 00:05:19,790 --> 00:05:18,030 performed subsequently the bulkhead was 102 00:05:21,980 --> 00:05:19,800 cleaned and acid-etched 103 00:05:25,210 --> 00:05:21,990 then turned over in the turnover fixture 104 00:05:27,860 --> 00:05:25,220 to apply protective coating to the dome 105 00:05:29,600 --> 00:05:27,870 on March 30th the bulkhead was 106 00:05:31,760 --> 00:05:29,610 transferred to the vertical Assembly 107 00:05:35,630 --> 00:05:31,770 Building and positioned over liquid 108 00:05:37,610 --> 00:05:35,640 hydrogen cylinder number 6 during May 109 00:05:41,990 --> 00:05:37,620 the bulkhead and cylinder were joined 110 00:05:44,360 --> 00:05:42,000 together by a circumferential weld in 111 00:05:47,090 --> 00:05:44,370 fabrication worked on the s2s stage 112 00:05:48,710 --> 00:05:47,100 common bulkhead all meridian welds on 113 00:05:50,960 --> 00:05:48,720 the forward facing sheet have been 114 00:05:55,780 --> 00:05:50,970 completed the dollar section installed 115 00:06:00,500 --> 00:05:58,400 meridian and dollar section welding was 116 00:06:03,260 --> 00:06:00,510 also finished on the common bulkhead aft 117 00:06:07,760 --> 00:06:03,270 facing sheet for the bulkhead test tank 118 00:06:10,730 --> 00:06:07,770 during April liquid hydrogen tank 119 00:06:13,820 --> 00:06:10,740 cylinder fabrication for the s2s stage 120 00:06:15,530 --> 00:06:13,830 continued this quarter during April the 121 00:06:18,290 --> 00:06:15,540 quarter panels of cylinder number four 122 00:06:20,510 --> 00:06:18,300 were joined by vertical wells and the 123 00:06:22,940 --> 00:06:20,520 assemble cylinder was circumferentially 124 00:06:25,310 --> 00:06:22,950 trimmed vertical welding was also 125 00:06:30,260 --> 00:06:25,320 underway on quarter panels for cylinder 126 00:06:33,010 --> 00:06:30,270 number five at Essen IDs s two-stage 127 00:06:35,510 --> 00:06:33,020 propulsion test facility at Santa Susana 128 00:06:37,990 --> 00:06:35,520 construction of the battleship stage and 129 00:06:40,070 --> 00:06:38,000 KOCO one test stand is complete and 130 00:06:43,159 --> 00:06:40,080 installation of systems will be 131 00:06:45,920 --> 00:06:43,169 next quarter the coca for all systems 132 00:06:48,709 --> 00:06:45,930 test stand construction effort is also 133 00:06:57,619 --> 00:06:48,719 complete and the 60 turn capacity hoist 134 00:07:00,230 --> 00:06:57,629 is operational at the beginning of this 135 00:07:02,330 --> 00:07:00,240 quarter the s4b hydro static and dynamic 136 00:07:04,550 --> 00:07:02,340 test stages were in Douglas Aircraft 137 00:07:09,860 --> 00:07:04,560 company's vertical assembly towers at 138 00:07:11,779 --> 00:07:09,870 Huntington Beach the hydrostatic test 139 00:07:14,119 --> 00:07:11,789 stage was later moved from its assembly 140 00:07:16,100 --> 00:07:14,129 Tower and placed in the structures test 141 00:07:18,320 --> 00:07:16,110 building where strain gauges and other 142 00:07:20,420 --> 00:07:18,330 instrumentation devices were installed 143 00:07:24,110 --> 00:07:20,430 in preparation for the start of 144 00:07:26,839 --> 00:07:24,120 hydrostatic testing next quarter in 145 00:07:29,450 --> 00:07:26,849 assembly work on the s4b dynamic test 146 00:07:31,490 --> 00:07:29,460 stage welding of the locks and liquid 147 00:07:33,409 --> 00:07:31,500 hydrogen tanks as well as internal 148 00:07:36,080 --> 00:07:33,419 welding of the forward liquid hydrogen 149 00:07:38,240 --> 00:07:36,090 dome to the liquid hydrogen tank was 150 00:07:46,100 --> 00:07:38,250 completed in mid-march at Huntington 151 00:07:48,320 --> 00:07:46,110 Beach during this report period the s4 152 00:07:50,360 --> 00:07:48,330 be all system stage was processed 153 00:07:52,730 --> 00:07:50,370 through assembly towers one and two 154 00:07:54,800 --> 00:07:52,740 where necessary welding was accomplished 155 00:07:59,390 --> 00:07:54,810 and was installed in the hydrostatic 156 00:08:02,149 --> 00:07:59,400 tower at Douglas a Sacramento test 157 00:08:04,339 --> 00:08:02,159 facility satisfactory final inspection a 158 00:08:06,320 --> 00:08:04,349 facility contractor effort at the Gama 159 00:08:08,749 --> 00:08:06,330 complex test control center and 160 00:08:10,420 --> 00:08:08,759 instrumentation center was performed 161 00:08:14,390 --> 00:08:10,430 March 25th 162 00:08:16,459 --> 00:08:14,400 at SAC toes bata complex installation of 163 00:08:19,100 --> 00:08:16,469 instrumentation at beta test stands 164 00:08:21,110 --> 00:08:19,110 number one is continuing and cold flow 165 00:08:25,730 --> 00:08:21,120 testing of the battleship stage is 166 00:08:28,189 --> 00:08:25,740 expected to begin in June at beta test 167 00:08:30,140 --> 00:08:28,199 stand number 3 construction continued 168 00:08:32,449 --> 00:08:30,150 during the report period with completion 169 00:08:34,399 --> 00:08:32,459 scheduled next quarter the stand will be 170 00:08:46,180 --> 00:08:34,409 used for test programs with the all 171 00:08:51,440 --> 00:08:49,220 on April 21st at the rocket engine test 172 00:08:55,190 --> 00:08:51,450 site Edwards Air Force Base during the 173 00:08:58,010 --> 00:08:55,200 informal pfr t on f1 R&D engine number 174 00:09:01,220 --> 00:08:58,020 oh one nine a LOX pump explosion 175 00:09:03,320 --> 00:09:01,230 occurred at 111 seconds into the run the 176 00:09:04,910 --> 00:09:03,330 test stand suffered damage similar to 177 00:09:06,980 --> 00:09:04,920 that which occurred during the previous 178 00:09:10,130 --> 00:09:06,990 puff explosion on engine number oh one 179 00:09:12,440 --> 00:09:10,140 four in February approximately three 180 00:09:14,750 --> 00:09:12,450 weeks were required for Stan's repair as 181 00:09:17,510 --> 00:09:14,760 a result of the April explosion all 182 00:09:20,210 --> 00:09:17,520 engine system in turboprop testing with 183 00:09:22,160 --> 00:09:20,220 LOX was halted while a team composed of 184 00:09:24,440 --> 00:09:22,170 members from Rocketdyne and Marshall 185 00:09:24,980 --> 00:09:24,450 conducted a thorough investigation of 186 00:09:27,730 --> 00:09:24,990 the matter 187 00:09:32,019 --> 00:09:27,740 testing was resumed May 15th after 188 00:09:35,060 --> 00:09:32,029 incorporation of recommended changes 189 00:09:38,750 --> 00:09:35,070 production test stand one D at Edwards 190 00:09:43,430 --> 00:09:38,760 was completed this quarter work on stand 191 00:09:47,420 --> 00:09:43,440 1 C is in its final phases stand 1e 192 00:09:49,160 --> 00:09:47,430 activation is due in the fall the 193 00:10:00,079 --> 00:09:49,170 control center at the production test 194 00:10:04,489 --> 00:10:02,480 at the Marshall Center prior to the 195 00:10:06,710 --> 00:10:04,499 April 21st explosion at Edwards 196 00:10:09,650 --> 00:10:06,720 propulsion system testing of the first 197 00:10:12,489 --> 00:10:09,660 f1 production engine continued with five 198 00:10:19,069 --> 00:10:12,499 firings for a total main stage time of 199 00:10:20,989 --> 00:10:19,079 196 seconds the second production engine 200 00:10:23,869 --> 00:10:20,999 was delivered to Marshall by Rocketdyne 201 00:10:26,210 --> 00:10:23,879 on April first quality lab completed its 202 00:10:28,249 --> 00:10:26,220 receiving inspection on April 14th and 203 00:10:30,199 --> 00:10:28,259 the engine was delivered to test lab 204 00:10:35,569 --> 00:10:30,209 where it is undergoing pre test 205 00:10:38,030 --> 00:10:35,579 preparation overall construction of the 206 00:10:40,549 --> 00:10:38,040 f1 engine static test standard Marshall 207 00:10:44,590 --> 00:10:40,559 has reached 80% completion with 208 00:10:47,840 --> 00:10:44,600 beneficial occupancy due next quarter 209 00:10:49,790 --> 00:10:47,850 rocky turns first j2 production engine 210 00:10:51,710 --> 00:10:49,800 was accepted by the Marshall Center this 211 00:10:53,900 --> 00:10:51,720 quarter the engine was turned over to 212 00:10:57,019 --> 00:10:53,910 Douglas Aircraft for use in captive 213 00:11:08,670 --> 00:10:57,029 tests associated with s4b battleship 214 00:11:13,950 --> 00:11:11,579 a series of engine system static tests 215 00:11:16,560 --> 00:11:13,960 was conducted during this report period 216 00:11:19,079 --> 00:11:16,570 to demonstrate full gimble capability as 217 00:11:21,090 --> 00:11:19,089 well as safety limits malfunction and 218 00:11:24,960 --> 00:11:21,100 full propellant utilization valve 219 00:11:27,630 --> 00:11:24,970 operation prior to entering PF RT the 220 00:11:29,550 --> 00:11:27,640 engine was gimballed twice to a seven 221 00:11:32,340 --> 00:11:29,560 degree limit in four different planes 222 00:11:34,740 --> 00:11:32,350 with three passes in each plane and to a 223 00:11:46,230 --> 00:11:34,750 10 degree gimble angle in the corners on 224 00:11:48,510 --> 00:11:46,240 another test a full-scale mock-up 260 225 00:11:50,160 --> 00:11:48,520 inches in diameter of the Saturn 5 226 00:11:52,290 --> 00:11:50,170 instrument unit was under construction 227 00:11:54,990 --> 00:11:52,300 at the Marshall Center during the report 228 00:11:57,360 --> 00:11:55,000 period to assist engineers improving out 229 00:11:59,340 --> 00:11:57,370 designs related to electrical cable 230 00:12:01,860 --> 00:11:59,350 length and routing instrument and 231 00:12:05,880 --> 00:12:01,870 bracket tree fittings and the IU cooling 232 00:12:09,199 --> 00:12:05,890 system the mock-up is now about 50% 233 00:12:13,260 --> 00:12:11,250 International Business Machines new 234 00:12:16,140 --> 00:12:13,270 facilities at Huntsville will be the 235 00:12:18,750 --> 00:12:16,150 site of Saturn 5 iu engineering and 236 00:12:21,300 --> 00:12:18,760 check-out work IBM was selected by NASA 237 00:12:24,920 --> 00:12:21,310 this quarter as lead contractor for 238 00:12:27,840 --> 00:12:24,930 development and fabrication of the IU 239 00:12:29,970 --> 00:12:27,850 the first computer and computer tester 240 00:12:32,160 --> 00:12:29,980 an early development model of the flight 241 00:12:34,560 --> 00:12:32,170 configuration equipment depicted in this 242 00:12:36,870 --> 00:12:34,570 artist's drawing was accepted this 243 00:12:45,000 --> 00:12:36,880 quarter from IBM for use in the IU 244 00:12:47,250 --> 00:12:45,010 breadboard construction of the Saturn 5 245 00:12:50,280 --> 00:12:47,260 dynamic test standard Marshall is now 246 00:12:54,030 --> 00:12:50,290 approximately 80% complete beneficial 247 00:12:56,370 --> 00:12:54,040 occupancy is scheduled in August at 248 00:12:58,769 --> 00:12:56,380 Marshall's Saturn 5 ground support 249 00:13:01,410 --> 00:12:58,779 equipment test facility depicted in this 250 00:13:03,269 --> 00:13:01,420 artist's drawing brick and mortar 251 00:13:05,190 --> 00:13:03,279 construction is approximately 35% 252 00:13:08,130 --> 00:13:05,200 finished the Technical Systems 253 00:13:09,900 --> 00:13:08,140 contractor is approximately 85% complete 254 00:13:12,300 --> 00:13:09,910 with all equipment scheduled for 255 00:13:14,310 --> 00:13:12,310 delivery by June installation of the 256 00:13:19,660 --> 00:13:14,320 Technical Systems is scheduled to start 257 00:13:24,960 --> 00:13:21,790 Mississippi test facility construction 258 00:13:28,360 --> 00:13:24,970 is continuing under three main complexes 259 00:13:30,850 --> 00:13:28,370 the test complex including excavation 260 00:13:34,810 --> 00:13:30,860 and foundation work on the s 1 C dual 261 00:13:38,980 --> 00:13:34,820 position static test and and the 2 s 2 262 00:13:41,200 --> 00:13:38,990 static test stands the laboratory and 263 00:13:43,030 --> 00:13:41,210 engineering complex which includes the 264 00:13:45,940 --> 00:13:43,040 office and administration building 265 00:13:50,080 --> 00:13:45,950 and the telephone and terminal building 266 00:13:52,060 --> 00:13:50,090 and the support services complex which 267 00:13:55,540 --> 00:13:52,070 encompasses such facilities as the 268 00:14:00,240 --> 00:13:55,550 emergency services building the MTF 269 00:14:04,210 --> 00:14:00,250 warehouse the site maintenance building 270 00:14:08,200 --> 00:14:04,220 the central heating plant and the 271 00:14:11,220 --> 00:14:08,210 electrical substation work also 272 00:14:17,430 --> 00:14:11,230 progressed steadily under various roads 273 00:14:20,320 --> 00:14:17,440 railway facilities river channels docks